View and manage scheduled future events for a schedule job
-
Update a template job to display the CCREGN—Job Detail screen.
- Select the Schedule tab.
To view future events:
- Select the Future Events tab.
Note that for future events to be previewed, at least Scheduled Times, Scheduled Days and Scheduled Months needs to be specified in the schedule details.
- Enter the Preview Until date.
- Click Preview.
For the preview to proceed, the schedule details must be valid. A valid schedule comprises the Scheduled Months and Scheduled Times, and either the Scheduled Weeks and Scheduled Days, or the Scheduled Days of Month.
The future event date-times, to a maximum of 100 future event date-times, are determined by the system based upon the schedule details, starting from the current server date-time, and displayed in the grid in chronological order with the earliest date-time displayed first.
To deactivate or activate a future event:
- Uncheck or check Is Active, as required.
- Click Submit.
To add a future event date that is not part of the scheduled frequency:
- Select the Future Events tab.
- Click
Add. - Enter a date-time that is in the future into Future Event Date.
- Click Submit to add the future event date as active and redisplay the grid in chronological order with the earliest date-time displayed first.