Configure drill integration fault reprocessing times

Configure reprocessing times if faults should be reprocessed as a batch; for example, at a time of day when drilling is likely to be complete. If you do not configure reprocessing times, faults are reprocessed at calculated times.

Note: This activity is not needed for WencoMine because that interface uses a database timestamp to identify which log entries need to be processed. See Configure WencoMine drill integration.

Activity steps:

  1. On the DataBlast application menu, select Site Maintenance.

    The Site Maintenance screen displays.

  2. Select the Service Control node.
  3. Select the Drill Machine Import > IMS Reprocessing Times tab.
  4. To add a reprocessing time:
    1. Click Add Process Time.
    2. Enter the Time of Day in the format HH:MM:SS.
    3. Select the Drill Machine System to Reprocess from Atlas Copco, Atlas Copco Auto, Carlson, Flanders, IMS, Jigsaw, MiPlan, Modular, Terrain, WencoLite and WencoMine.

      Note: You can select multiple systems for each reprocessing time, and you can select both active and inactive drill machine integrations in this configuration.

  5. To remove a reprocessing time:
    1. Click the arrow row selector for the time.
    2. Press Delete (on your keyboard).

      A confirmation message displays.

    3. Click Yes.
  6. Click Save Changes.