Update Project
This option opens the Update Procedure screen, which allows you to update the completion details of your project based on the current date.
Field | Description |
Set all work before update date as complete | Select this field to set as complete all tasks or portions of tasks that fall before the Update date. |
Reschedule uncompleted work to start after update date | Select this field to delay all incomplete tasks before the
update date so they occur on or after the update date.
By default, this field is selected. |
Stretch to date | Select this field to stretch all incomplete activities that fall before the update date to the update date. |
Update Date | Specifies the date when the project is to being updated to.
By default, this date is set to today's date. Click |
Last Updated On | Specifies the date when the project was last updated.
Click |
For | Specifies the scope of the update process.
|
Update | Click to save your changes and close the screen. |
Close | Click to lose the changes you made and close the screen. |
![]() |
Click to display the help for this screen. |