Update Project

This option opens the Update Procedure screen, which allows you to update the completion details of your project based on the current date.

Field Description
Set all work before update date as complete Select this field to set as complete all tasks or portions of tasks that fall before the Update date.
Reschedule uncompleted work to start after update date Select this field to delay all incomplete tasks before the update date so they occur on or after the update date.

By default, this field is selected.

Stretch to date Select this field to stretch all incomplete activities that fall before the update date to the update date.
Update Date Specifies the date when the project is to being updated to.

By default, this date is set to today's date. 

Click  to display a calendar and select another date.

Last Updated On Specifies the date when the project was last updated.

Click  to display a calendar and select another date.

For Specifies the scope of the update process.
  • Entire project - all tasks in the project are updated.
  • Selected tasks - only the selected tasks are updated.
Update Click to save your changes and close the screen.
Close Click to lose the changes you made and close the screen.