Generate a Complex Work Pattern
-
Home ribbon >> Project Settings >> Calendars >> Scheduling Calendars.
The Scheduling Calendars screen displays.
- Using the Calendar list toolbar, either pick an existing calendar or click New to create a new one.
- Click Generate
- Select the start and end dates (e.g. 1 Jan 2013 - 31 Dec 2013) over which to repeat the pattern.
- Select the Generate a repeating pattern option to repeat the pattern over the selected date range.
- Add some record into the grid below the option. Specify a
type (Work, No Effect, Holiday, Default), the number of days to
apply the record and some shifts for the Work type.
- No Effect - the number of days will not be changed
- Default - the number of days is set back to the default for the calendar
- Work - the working periods specified in the Shift field is applied
- Holiday - the number of days is set as holidays
- The pattern will repeat between the specified start and end dates. When the last record is reached, the pattern will restart at the first record.
- Press Generate to apply.
- You can change some parameters and generate some other periods, or press Close to exit the screen.