Generate Holidays
- The Project Settings form can be opened by using the Project Settings button
on the Home page of the ribbon.
- Select the Scheduling Calendars option under the Calendars section of the tree in the form.
- Select the relevant calendar in the calendar list on the page.
- Press the Generate button.
- Select the start and end dates (e.g. 1 Jan 2013 - 31 Dec 2013) over which to generate the holidays.
- Select the Repeat day of the week option to repeat the pattern for every week in the selected date range.
- Set the frequency of the generation, e.g. every 2 weeks.
- Select the days of the week to apply the working periods to, e.g. Sunday.
- Select the Change selected days to holidays option.
- Press Generate to apply.
- You can change some parameters and generate some other periods, or press Close to exit the screen.