Add a Unit Cost Field

Activity steps:

  1. Display the Production Fields screen.
  2. Select the blank row at the end of the table.
  3. Enter a unique Field name, for example; Fixed Cost
  4. Define the Unit for the production field.
  5. Select the production field to base the cost on, for example; Tons.
  6. Change the Cost Field value to Task.
  7. Specify unit cost values (per ton) for each task.
  8. Click OK.
  9. Save your project.

Related information and activities