Mark a Specific Week Day as Non-working
- The Project Settings form can be opened by using the Project Settings button
on the Home page of the ribbon.
- Select the Scheduling Calendars option under the Calendars
section of the tree in the form.
- Select the relevant calendar in the calendar list on the page.
- Use the mouse to select the relevant week day (e.g. Sunday) at
the top of calendar grid.
- Press the Non-Work button to change the week day by default to
non-work.
- Press the Close button to apply the changes.