Remove all splits
- Find the bar representing the task in the Gantt chart.
- Move the mouse cursor onto the bar and click the right mouse button.
- Select the Remove All Splits option from the context menu.
- The splits for the task is removed and the task scheduled in one continuous duration.
or
- Select a block of tasks in the spreadsheet.
- Move the mouse cursor onto the bar and click the right mouse button.
- Select the Remove All Splits option from the context menu.
- The splits for all selected tasks is removed and each task scheduled in one continuous duration.
Note When the percentage complete is set on a task, it is automatically split into the completed and remaining sections. You cannot remove this automatic split unless you set the percentage complete to 0 or 100.