Add a Stripping Ratio Field
- The Project Settings form can be opened by using the Project Settings button
on the Home page of the ribbon.
- Select the Summary Fields option under the Fields section of
the tree in the form.
- In the blank row at the bottom of the grid enter a name for
field in the Name column. The name must be unique in the project.
- Click the cell in the Expression column to open the popup grid.
- In the Field column of the popup grid select the production field that represent
the waste tons of material scheduled.
- In the Filter column select a task filter that filters out the
waste blocks.
- Press OK to close the popup grid.
- In the Operator column select the / (division) operator.
- Click in the second Expression column to open the popup grid.
- In the Field column select the production field that
represent the ore tons scheduled.
- In the Filter column select a task filter that filters
out the ore blocks.
- Press OK to close the popup grid.
- Press Close to apply the changes.