Mine Closure Plan (WA)

DMP Mine Closure Web Site

  • All tenements that have an approved Mining Proposal must also have an approved Mine Closure Plan (MCP).
  • MCP is prepared in accordance with the Guidelines for Preparing Mine Closure Plans (MCP).
  • Approved MCPs must be reviewed after three years or at a time specified by DMIRS.
  • The updated MCP including any changes must then be submitted again to DMIRS for approval.
  • The due date of the revised MCP is specified as a tenement condition.
  • MCPs can be lodged electronically with a mining proposal, in hard copy at DMIRS offices, or online via DMIRS submissions.