View the Chart of a Production and Demand Plan
Security Note: Assuming you can view the plan, no specific security right is required for this activity.
Activity Steps
- Open the Plan.
- Select the Chart tab.
- Enter the following search criteria as required.
- Start Date—Default: As selected on the Worksheet tab. These dates must be within the range of the Plan Start Date and Plan End Date.
- End Date
- To modify the appearance of the chart:
- Right-click the chart and select Show Wizard from the menu.
The Chart Wizard displays.
- Select the Series tab.
- Select the products and brands to be displayed as a line on the chart.
- Edit other chart properties as required.
- Click Accept.
- Right-click the chart and select Show Wizard from the menu.
- To save the chart as a BMP, GIF, JPEG, PNG or TIFF image, right-click the chart and select Save To File from the menu.