Compare Forecast and Actual Quantities of a Mine Plan
Security Note: Assuming you can view the mine source, no specific security right is required for this activity via a mine source. You need the Allow planning maintenance security right in the Planning domain security rights group for this activity via a mine plan.
Activity Steps (via a Mine Source)
- Open the Mine Source.
- Select the Mine Plans tab.
Activity Steps (via a Mine Plan)
- Open the Mine Plan.
- Enter the following search criteria in the Mine Plan Forecasts field group.
- Start Date
- End Date
- Click Refresh.