Mining Analysis Results
- Chart information – plan type, tonnes and grade. Note that if the information icon is clicked, the plan name will be shown.
- Metrics – The Direct Feed, Stockpiling and Waste Movements metrics are grouped according to the individual grouping in the configure panel. The percentage value associated with each metric relates to the planned / actual tonnes variance for that particular metric.
- Mine Production Metric – Total of Direct Feed, Stockpiling and Waste production. The variance is the total planned / total actual production.
- Planned Production – Dependent on the mine plan that is selected in the configure panel and is displayed in the chart title (1.) The table provides the detail of tonnes and grade for each component of the metric defined by the grouping selected in configure panel.
- Actual Production – Mine Production where the source was the mine.
- Waterfall chart representing the mine production changes from the selected plan.
- Mine Plan Compliance – How well the mine is complying with the plan based on the lowest location level in the plan. So in the example above the mining only has a 30% compliance to the Short Term Plan (Ore and Waste) for the period selected. Using the configure panel, in the Mine Plan Compliance section, the user can choose to compare tonnes based on survey (measured) or truck tonnes.
- The waterfall chart on the mine plan compliance section shows planned tonnes on the left, through to mined tonnes on the right. Note the following:
- Planned & Not Mined + Planned & Mined = Planned
- Planned & Mined + Mined & Not Planned = Mined