Scheduler: Quick Start
Prior to accessing the Settings screen for scheduling, you'll need to complete the following:
-
Choose pushback input other than the default Pushback Generator Optimal Extraction Sequence (OES), for example, imported pushbacks.
-
Define haulage information.
-
Define capital costs associated with pushback startups or time periods (or both).
-
Edit the time period settings.
-
Define at least one scheduling target and choose a primary scheduling objective. Note that if you have provided haulage information, you can use the DistByMass variable to define truck hours related targets.
Note: Maximum sinking rate and pushback start after dates are optional.
-
Review the control parameters.
Note: The rescheduling option will become available only after you have run the Scheduler at least once. If selected, this option replaces the input OES with the most recent Scheduler OES.
-
Using the Pushbacks screen, you can review the default pushback K-bench dependencies and adjust them if necessary. The first two Mining order options guarantee the correct slopes; the Custom option does not unless the dependencies are set correctly.
Note: Mine Flow Optimization (MFO) and Material Allocation Optimization (MAO) are fully integrated in Studio NPVS+ meaning additional optimization isn't required. As such, these modules do not appear in Studio NPVS+.