Capital Costs
To access this screen:
-
Optimization task bar >> Scheduler >> Capital Costs.
Define Capital Costs for the Scheduler. You define obstacle removal costs prior to pit optimization and all other capital costs prior to scheduling.
Costs can be defined on a per-pushback and per-period basis, with each category defined in a separate table.
Note: You can specify a maximum of 50 rows for pushbacks and time periods.
To define capital costs for the scheduler:
-
Display the Capital Costs screen.
-
Use the Capital costs by pushback table to specify for each Pushback Index, the capital Costs on the day when the mining of the pushback begins; enter the investment amount.
-
Similarly, for per-period costs, use the lower table to specify the time Period index, and the money spent on the first day of the that time period.
Related topics and activities: