Capture Daily Actual Resource Values
- Locate the resource in the cross-tab chart.
-
Double-click the left mouse button while the mouse cursor is over the row in the table representing the resource.
The Resource Information screen displays.
- Select the Actuals tab.
- Select the production field in the list that you want to track daily measurements for, for example; Actual Tons.
- Enter reading dates and corresponding actual values. Each actual value is the total recorded for the corresponding day - not the total for the resource to date.
- Press OK.
Note: You can only capture daily resource measurements for production fields with Track Actual checked and Record Actuals On set to Resource.