Add a Grade Production Field
Activity steps:
- Display the Production Fields screen.
- ADD MENU
- Select the blank row at the end of the table.
- Enter a unique Field name, for example, AU.
- Define the Unit for the production field.
-
In the Weighted by column select the production field to weight the grades on, say, Tons.
Grade values are generally entered as percentages or fractions (such as Fe = 67.3%, Au = 5.7 g/ton).
Note: The weighting property is used as a weighting factor when the average grade of a period in the schedule is calculated from all the tasks scheduled over the period.
- Click OK.
- Save your project.
Related information and activities