Capture Daily Actual Project Values

  1. Display the Project Settings screen.
  2. Using the vertical menu system, select Fields >> Production Fields.
  3. Select the field you want to capture actual values for in the grid.
  4. Below the fields table, select the Actuals tab.
  5. Enter dates and corresponding actual values for the selected production field into the Actuals grid.

    If you skip dates, the system will automatically add days with zero values.

Note: You can only capture daily measurements on a project level for production fields with Track Actual checked and Record Actuals On set to Property.