Level Resources
-
Tools ribbon >> Leveling >> Level.
The Resource/Target Leveling screen displays.
Tip: You can also press F10 to display the same screen.
- Select the algorithm and the fields to prioritize the tasks in the Details page.
- If you want to decide how the schedule operates, review and edit the Tuning parameters.
-
Press Level Now to calculate and level your schedule's resources.
Note: DTS will delay some tasks until sufficient resource capacity is available by setting leveling constraint dates on the tasks or sections.