Go To Selected Task

Position the Gantt chart display at the currently selected task in the Task Table area.

Activity steps:

  1. Select the task where you want the Gantt chart display to be positioned.
  2. Do one of the following:
    1. Home ribbon >> Find >> Locate Bar.
    2. Click Go to Task on the Status Bar.

Related topics and activities