Append New Data to a Drillhole Project

Drillhole project data imported from an Access database can have data added to the drillhole project if new data has been added to the source files.

  1. On the Discover ribbon tab, in the Drillhole Project group, click Append Drillhole Data.

    A loading window displays.

    Discover uses the following rules to determine if new data exists in the source files:

    • Collar file—Checks the HoleID.
    • Survey file—Checks the HoleID and survey point depth.
    • Downhole data files—Checks the HoleID and From and To intervals.
  2. The data must be revalidated. See Validate Imported Drillhole Data.