Unload Bulk Material from a Train

A process flow with the loading rail siding as a source is required for train bulk unloading. The train template may limit the available process flows and source stockpiles.

This activity is not required if the train was created using a template with Auto Unload checked.

Security Note: You need the Allow train loading/unloading security right in the Trains domain security rights group for this activity.

Activity Steps

  1. Open the Train.
  2. Ensure that the train structure has been defined for the train.
  3. Select the unloading route point in the Route diagram.
  4. Ensure that Loading / Unloading in the train header field group is Unloading. This setting depends on the route configuration. See Edit the Route of a Train.
  5. Select the Unloading tab.
  6. If the Loading Type is By Wagon, and the train was created using a template with a default unloading process flow and stockpile defined, and more than one train wagon is defined, to manually create all unloading transactions for each defined wagon:
    1. Right-click in the Bulk Transactions table and select Unload All Wagons from the menu.

      MineMarket creates an unloading transaction for each wagon, in the defined order on the Structure tab. The Source for each transaction is a train wagon.

    2. Update the following fields for each transaction.
      • Number Of Units—Optional.
      • Mass—Amount of material unloaded on an as-received (wet) basis. If the mass is outside planned limits, the mass is highlighted in red. If a tonnage correction is applied to the transaction and a back calculation is performed, the mass is updated to display the corrected mass and the field is read-only.
      • Unit—Select from the Mass units defined in the Unit Conversion Editor. Default: Metric tonnes. However, if the despatch is based on a despatch template, the default UOM is the template UOM. If a different UOM is specified for loading, the UOM of the first loading transaction becomes the default UOM for any unloading transactions. This field is read-only if a back calculation has been performed in a tonnage correction. Selecting a different unit for a single transaction does not convert any mass already entered. Selecting a different unit on the Total row displays the total mass and original mass converted into that unit; however, this does not modify any values stored in MineMarket.
      • Movement Product—Select from the Allowed Movement Products specified for the process flow. Set to the movement product of loading transactions if the template has Use Loaded Product When Unloading All Wagons checked.

        Note: The Product is read-only. Both the Product and default Movement Product depend on whether the source or destination stockpiles have an assigned product. See Material Flows.

  7. To manually create unloading transactions:
    1. Right-click in the Bulk Transactions table and select New Unloading Transaction from the menu.
    2. Update the following fields for the transaction.
      • Start Date—Optional.
      • Transaction Date—Default for first transaction: Start Unloading - Actual if specified on the Route Plan tab; or else the current system date and time and MineMarket updates Start Unloading - Actual with that time.
      • Process Flow—Select from the process flows defined on the Supply Chain panel of the Solution Explorer and that have the unloading rail siding as a source.
      • Source—Select from the train rakes if the Loading Type is By Rake. Select from the train wagons if the Loading Type is By Wagon.
      • Destination—Select from the stockpiles at the destination location of the process flow. If unloading directly to another despatch, select from the vessel holds, barge holds, train rakes or wagons, or trucks that are at the destination location of the process flow at a suitable time.
      • Number Of Wagons—Optional.
      • Number Of Units
      • Mass
      • Unit
      • Movement Product
  8. If the unloading transaction corresponds to one despatch order, select the Despatch Order. Select from the despatch orders associated with the train. If there is only one despatch order, it is selected by default.
  9. To use the unloading transaction as an emptying transaction for a bulk package group, select the Package Group. This association is appropriate when unloading containers that are already on the train.

    The corresponding emptying transaction can be viewed (but not edited) on the Bulk Storage tab of the Package Group (Bulk).

    Select from package groups that meet all the following criteria:

    • The package group's Despatch Order matches the despatch order associated with the bulk transaction.
    • The package group is in a selectable status (or no status definition for package groups exists).
    • The package group is active and unlocked.
    • The package group's Opening Date is before the transaction's Transaction Date.
    • The package group has an assigned Container Type.
    • The container type has a Storage Type of Bulk Only.

    Default: If the selected despatch order is associated with only one package group and the package group meets the above criteria, that package group is selected by default.

  10. To associate the unloading transaction with equipment, select the Equipment. Select from the equipment items assigned to the process flow.
  11. Select the Transport Operator if required. Select from the train operators defined on the Transport Operators screen.
  12. Click Save.

    Note: If automatic despatch order fulfilment is configured for the contract product, saving the transaction may have an impact on whether the despatch order is fulfilled, and on the despatch order status. See Despatch Order Fulfilment.