Compare Planned Movements with Actual Transactions
Security Note: You need the Allow planned movement modifications security right in the Planning domain security rights group for this activity.
Activity Steps
- Open the Planned Movements screen for the location or process flow.
- Select the Planned V Actual tab.
- Enter the search criteria:
- Select the Start Date and End Date.
- Select the method to Group By if required. Select from Nothing, Process Flow, Source Stockpile, Destination Stockpile and Product.
- Select the Date Period from Shift, Day, Week, Fortnight and Month.
- If the Date Period is Shift, select the Shift from the shifts defined on the Supply Chain panel of the Solution Explorer.
- Click Search or press F3.
The aggregated planned movements and actual transactions display as a table and a chart.
- To modify the appearance of the chart:
- Right-click the chart and select Show Wizard from the menu.
The Chart Wizard displays.
- Edit the chart properties as required.
- Click Accept.
- Right-click the chart and select Show Wizard from the menu.
- To save the chart as a BMP, GIF, JPEG, PNG or TIFF image, right-click the chart and select Save To File from the menu.