Enter a Mine Plan Forecast

Security Note: Assuming you can view the mine source, no specific security right is required for this activity.

Activity Steps

  1. Open the Mine Source.
  2. Select the Mine Plans tab.
  3. Select the mine plan in the Mine Plans table.
  4. Right-click in the Mine Source Forecasts field group and select New from the menu.
  5. Enter the following details for the mine source forecast.
    • Start Date—Date from which the Quantity of Product should be extracted from the mine source.
    • Completion Date—Date up to which the Quantity of Product should be extracted from the mine source.
    • Quantity
    • Unit—Select from the Mass units defined in the Unit Conversion Editor.
  6. Click Save.