Confirm stockpile movement parameters

Stockpile Movement

To access this dialog:

The Schedule Selected Blocks dialog's Stockpile Movement tab is used to define, preview and then schedule stockpile material for the selected period.

 

Field Details:

Period: select a period from the dropdown.

note.gif (1017 bytes)

 The <Right> and <Left> keyboard keys can also be used to move between periods.

 

Tonnes Mode: select this option to display Tonnes values in the grid.

Volume Mode: select this option to display Volume values in the grid.

Hide Empty Stockpiles: tick this box to hide empty stockpile grid entries.

Stockpile Movement grid: this grid lists the stockpiles and their associated stockpile, destination and machine parameters for the selected period.

Stockpile: stockpile name.

Reclaim Date: double-click to define a date for reclaiming the stockpile material.

Reclaim Time: double-click to define a time on the specified Reclaim Date for reclaiming the stockpile material.

Tonnes/Volume: amount of stockpile material to be scheduled on the specified Date and Time.

Available Tonnes/Volume: total amount of material on the stockpile available for scheduling in the selected period .

Max Reclaim (tonnage): the maximum amount of material that can be reclaimed per period.

Destination: select a destination for the reclaimed stockpile material.

Loader: select a loader that will be used to handle the stockpile material. This will only display valid loaders.

Preview: preview and validate the defined grid parameters, optionally log the haulage calculation results.

Clear Preview: clear the grid preview.

OK: schedule the selected material, save changes and close the dialog.

Cancel: close the dialog without scheduling material or saving changes.

 

Haulage Calculation

Stockpile modelling haulage is calculated for Supply and  Reclaim activities. It works the same way in dump haulage

Stockpile Movement Grid Parameters

The tonnage available is shown for each Stockpile. The Maximum Reclaim rate and Available Tonnage is shown for the stockpiles, if they have been set up as Destinations. A warning message is given if the user attempts to reclaim more than the maximum rate or more than the tonnage available.

The available Destination depends on the Rock Types enabled in Destination Rocktype Settings. ISTSStudioOP requires that every Rock Type must be enabled for at least one Destination before the ISTSStudioOP scheduler can be used.

Where Set All is shown in the TOTAL row the value can be selected from a drop down list.

 

 

Modifying the Stockpile Movement Grid Parameters

  1. In theStockpile Movement grid, locate the required category's parameter,

  2. Using the relevant dropdown list, select the new parameter.