Undo Mining
To access this screen use one of the following:
-
Activate the Schedule ribbon and select Schedule >> Undo.
The Undo Mining screen is used to define the parameters and then unschedule mining blocks and stockpiles for the defined period(s).
This function allows you to remove mining, of any activity type (although it should be noted that process flow order must still be observed so you cannot remove an activity which is required by another activity unless that too is removed).
The removal can be by selection, machine type or
period limits.
Activity steps:
-
Set Period and choose one option:
-
All for all periods.
-
Current for the current period.
-
Subsequent for periods after the current period.
-
Range to use the period range defined by From and To.
-
-
If Range is selected, set From and To to define the undo-mining period range.
-
Set Source 1:
-
[All] for mining blocks and stockpiles.
-
[Blocks] for mining blocks only.
-
[Stockpiles] for stockpiles only.
-
[Mining Shapes] for mining shapes only.
-
-
Set Source 2 based on Source 1:
-
If Source 1 = [Blocks], choose [All] or [Selected] (selected mining block outlines in the 3D window).
-
If Source 1 = [Stockpiles], choose [All] or [Stockpile Name] from the drop-down list.
-
If Source 1 = [Mining Shapes], choose [All] or [Selected] (selected mining shapes in the 3D window).
-
-
Set Destination to [All] or a specific [Destination Name].
-
Set Machine Type:
-
[All] for all machine types.
-
[Machine Type] to select a machine type name from the drop-down list.
-
[Selection] for selections in the 3D window.
-
-
If a machine type is selected, set Machine 2 to [All] or a specific [Machine Class].
-
Set Activity to [All] or a specific [Activity Type].
-
Click OK to close the screen and undo mined blocks and stockpiles using the defined criteria.
-
Click Cancel to close the screen and cancel undo mining.