auto-progress-switch ("tap")

See this command in the command table.

To access this command:

Command Overview

Toggle switch for automatic scheduling when using change-period.

Command steps

  1. Run the command.

  2. One of two interchangeable states becomes active:

  • active mine faces or tonnages will be automatically mined when the scheduling calendar period is next advanced.

  • active mine faces or tonnages will not be automatically mined when the scheduling calendar period is next advanced.

Note: When the command change-period is used to advance by one calendar period, any active mine faces or tonnage zones may be automatically mined through in the new period. The auto-progress-switch command toggles this automatic mining. If it is necessary to move around different periods in the schedule, without affecting it directly, the toggle switch should be turned off.