MAO Haulage Information: Haulage Sources used to add or modify the MAO haulage information |
MAO Haulage Information: Haulage Sources
To access this dialog:
-
Using the Optimization control bar, select Allocation & Flow | Haulage Info... and select the Haulage Sources tab.
The Haulage Sources dialog is used to define the truck parameters for each material source (mine and/or stockpiles). In a Multimine project each mine is listed in this dialog.
Each mine can use its own truck type. Stockpiles can use their own truck type and these can be different from the mine truck types.
Field Details:
Haulage Sources: used to set from where the material is hauled (a mine, a stockpile or external source) including truck parameters and ramp parameters.
Truck Parameters:used to define the following parameters: Reference Speed, Avg Wait at load Point, Loading Time, Dumping Time, Total Wait Time, Truck Availability, Truck Size.
Ramp Parameters: these parameters can be set to 0 for stockpiles
Down Ramp Speed (km/h): average truck speed going down the ramp in kilometers or miles per hour
Up Ramp Speed (km/h): average truck speed going up the ramp in kilometers or miles per hour
Ramp Gradient (%): ramp gradient in percent
Truck and Ramp Parameters: window B displays (two truck types were defined) and is used to define the following parameters: Reference Speed, Avg Wait at load Point, Loading Time, Dumping Time, Total Wait Time, Truck Availability, Truck Size.
With two truck types: selectable options buttons display for either ore or waste truck types
For ore carrying truck: option button used to define the parameters of an ore carrying truck
For waste carrying truck: option button used to define the parameters of a waste carrying truck
Each truck type has specific parameters and these are defined for each material source.
The parameters can be reset to the settings defined under Haulage Information within the Scheduler group, or they can be defined here.
Ramp Parameters: these parameters can be set to 0 for stockpiles
Down Ramp Speed (km/h): average truck speed going down the ramp in kilometers or miles per hour
Up Ramp Speed (km/h): average truck speed going up the ramp in kilometers or miles per hour
Ramp Gradient (%): ramp gradient in percent
|
Related Topics |
|
MAO
Haulage Information - Haulage Destinations
Haulage Information: Exit Benches |
Copyright © Datamine Corporate Limited