Delay Task Start

Activity steps:

  1. Find the task you want to delay in the spreadsheet or Gantt chart.
  2. Double-click the task row in the Task Area table, or over the task bar in the Gantt chart.

    The Task Information screen displays.

  3. Change the Constraint Type to Start No Earlier Than and set a Constraint Date.
  4. Click OK.