Delay Task Start
Activity steps:
- Find the task you want to delay in the spreadsheet or Gantt chart.
-
Double-click the task row in the Task Area table, or over the task bar in the Gantt chart.
The Task Information screen displays.
- Change the Constraint Type to Start No Earlier Than
and set a Constraint Date.
- Click OK.
Related topics and activities