Change the Backfilled Status of Holes

If you enter backfill data for holes (see Enter Backfill Data), those holes are automatically flagged as backfilled. Use this activity to manually change the backfill status if required.

To flag holes as backfilled:

  1. Select the Measure module.
  2. Select a drill pattern in the DataBlast Items Tree.

    The drill pattern displays in the Viewport.

  3. Select or filter holes as required. See Select Objects in the Viewport and Filter Displayed Holes.
  4. On the Measure Ribbon Menu, in the Backfill group, click Flag as Backfilled.

    The Action Date/Time screen displays.

  5. Select the Action Date/Time from:
    1. Start of Current Shift (default)—For shift configuration, see Maintain Shifts.
    2. Current Date/Time
    3. Custom Date/Time—Update the Date and Time as required.
  6. Click OK.

    The Backfilled Date is updated in the Hole Properties.

    Note: A backfilled hole has 'as-built' data and cannot be modified in the Design Module.

  7. Click Save Changes.

To flag holes as not backfilled:

  1. Select the Measure module.
  2. Select a drill pattern in the DataBlast Items Tree.

    The drill pattern displays in the Viewport.

  3. Select or filter holes as required.
  4. On the Measure ribbon menu, in the Backfill group, click Remove Backfilled Flag.

    A confirmation message displays.

  5. Click Yes.

    The Backfilled Date is cleared in the hole properties.

  6. Click Save Changes.