Generate Exception Days
Generate a calendar that contains dates where exceptional working periods are to be worked.
Activity steps:
-
Home ribbon >> Project Settings >> Calendars >> Scheduling Calendars.
The Scheduling Calendars screen displays.
- Using the Calendar list toolbar, either pick an existing calendar or click New to create a new one.
- Click Generate.
- Select the start and end dates (e.g. 1 Jan 2013 - 31 Dec 2020) over which to generate the calendar.
- Check Repeat day of the weekto repeat the pattern for every week in the selected date range.
- Set the frequency of the generation, say, every 1 week.
- Select the days of the week to apply the working periods to, for example, Sunday and Saturday.
- Check Apply work periods to selected days.
- Enter the working periods that you want to apply to the selected week days in the Apply grid, for example, 0:00-12:00, 14:00-22:00.
- Click Generate.
- You can change selections and generate other periods, or click Close to exit the screen.