Reset Days to Default

  1. The Project Settings form can be opened by using the Project Settings button
    on the Home page of the ribbon.
  2. Select the Scheduling Calendars option under the Calendars section of the tree in the form.
  3. Select the relevant calendar in the calendar list on the page.
  4. Press the Generate button.
  5. Select the start and end dates (e.g. 1 Jan 2013 - 31 Dec 2013) over which to reset the exception days.
  6. Select the Repeat day of the week option to repeat the pattern for every week in the selected date range.
  7. Set the frequency of the generation, e.g. every 2 weeks.
  8. Select the days of the week to apply the working periods to, e.g. Monday up to Friday.
  9. Select the Set selected days to default option.
  10. Press Generate to apply.
  11. You can change some parameters and generate some other periods, or press Close to exit the screen.