Remove Splits after a Date

This activity lets you remove task splits from a specified date onward. A split divides one task into separate sections that can be scheduled independently. You must split a task before you can remove splits.

See Split a Task into Sections

Activity steps:

  1. Right-click a previously split task in either the Gannt chart and select Remove Split(s) After Date

  2. Review the Task ID. Edit it if you need to specify a different split task.

  3. In From Date, enter the date from which splits are removed.

  4. Click OK to remove all splits after the specified date.

Related topics and activities: