Remove Splits after a Date
This activity lets you remove task splits from a specified date onward. A split divides one task into separate sections that can be scheduled independently. You must split a task before you can remove splits.
See Split a Task into Sections
Activity steps:
-
Right-click a previously split task in either the Gannt chart and select Remove Split(s) After Date
-
Review the Task ID. Edit it if you need to specify a different split task.
-
In From Date, enter the date from which splits are removed.
-
Click OK to remove all splits after the specified date.