Capture Destination Actuals

Note: You can only capture actuals for stockpile and general destination types. See Destinations.

Activity steps:

  1. Display the Project Settings screen.
  2. Using the vertical menu system, select Destinations.
  3. Select a destination and select the State/Actuals tab.
  4. Select the field for which you want to capture actual values.
  5. Enter Dates and corresponding values (tons, area, and so on) for the selected production field(s) into table.

    Note: If you skip dates, the system will automatically add days with zero values.

  6. Click OK or Apply.