Bar Chart Options: Non-work Periods

This tab allows you to specify if and how you want to interrupt and/or highlight the Gantt bars during non-work periods based on the project's calendar.

The following table describes the fields on this tab shown below:

Note: You can use this option together with the Non-work Periods option in the Layout tab.

  Field Description
Interrupt bars during non-work periods These fields allow you to specify if and how you want the Gantt bar charts to be interrupted (show a gap) during non-work periods.
No Select this field if you do not want to interrupt the bars. By default, this field is selected.
Interrupt during non-work days falling outside the standard work-week

Select this file to interrupt any whole days of the year that are set to non-working periods due to holidays, vacation, shutdown, and so on. This excludes days of the week that are always non-working.

For example, if you have set a 5 day work week, Saturday and Sunday are non-working periods at all times and so are not interrupted.

Interrupt during all whole non-work days

Select this field to interrupt all standard or non-standard non-working days.

For example, if you have set a 5 day work week, Saturday and Sundays are always non-working and so they are always interrupted.

Interrupt during all non-work periods

Select this field to interrupt all whole and partial standard or non-standard non-working days.

For example, if you have set a 5 day work week, Saturday and Sundays, with Monday, Tuesday, Thursday, and Friday as 24-hour shifts and Wednesday as an 8-hour shift (from 8AM to 4PM),.then Saturday and Sundays and the partial non-working period on Wednesdays are always non-working and so they are always interrupted.

Highlight non-work periods These fields allow you to specify if and how you want to highlight the Gantt bars during non-work periods.
No Select this field if you do not want to highlight the bars. By default, this field is selected.

Highlight non-work days falling outside the standard work-week

(highlight all whole non-work days falling within the standard work-week)

Select this field to highlight any whole days of the year that are set to non-working periods due to holidays, vacation, shutdown, and so on. This excludes days of the week that are always non-working.

For example, if you have set a 5 day work week, Saturday and Sunday are non-working periods at all times and so are not highlighted.

Highlight all whole non-work days

Select this field to highlight all standard or non-standard non-working days.

For example, if you have set a 5 day work week, Saturday and Sundays are always non-working and so they are always highlighted.

Highlight all non-work periods

Select this field to highlight all whole and partial standard or non-standard non-working days.

For example, if you have set a 5 day work week, Saturday and Sundays, with Monday, Tuesday, Thursday, and Friday as 24-hour shifts and Wednesday as an 8-hour shift (from 8AM to 4PM),.then Saturday and Sundays and the partial non-working period on Wednesdays are always non-working and so they are always highlighted.

OK Click to save your changes and close the screen.
Close Click to lose the changes you made and close the screen.
Help Click to display the help for this screen.