Machines Control Bar

To show or hide this control bar:

  • Schedule ribbon >> Schedule Bars >> Machines.

The Machines control bar is used to display the machine usage for the selected Period. This includes the hours, capacity and tonnes information.

Tip: Use Previous Period and Next Period to move between displayed schedule periods.

How Hours are Calculated

The Period Hours grid column contains the duration (period length) as defined on the calendar screen

 

Period Hrs, Downtime Hrs, Available Hrs and Lead Duration are reported for each Activity (e.g. Loading). Operating Hrs, Remaining Hrs and Capacity are reported per fleet.  Fleet capacity is calculated as follows:

  • Period Hrs = Calendar Hrs

  • Downtime Hrs = [Mine Standby + Planned Maintenance]

  • Available Hrs = [Period Hrs – Downtime Hrs]

  • Remaining Hrs (Haul Truck) = [Available Hrs – (Truck Hrs /Utilisation)] x Utilisation

  • Remaining Hrs (Machines)  = [Available Hrs – (Lead Duration + Working Duration )] x Utilisation

  • Fleet Capacity (Machines) = Remaining Hrs x Unit Rate x Number of units

  • EFH Loaded = the total EFH loaded distance covered by that truck class over a period
    (loaded trip time x loaded flat haul speed x number of trips)

  • EFH Empty = the total EFH empty distance covered by that truck class over a period (unloaded trip time x unloaded flat haul speed x number of trips)  

Where the fleet consists of more than one machine the fleet can be thought of as a number of machines working in parallel. For example if you require to move 10,000 tonnes/day with 1 Machine rated at 2,000 tonnes per operating hour and a utilisation of 50%, the fleet capacity is calculated as follows:

  • Period Hrs = 24 hrs

  • Downtime = 0 hrs

  • Available Hrs = 24  

  • Operating Hrs = 10,000 tonnes /[2,000 tph x 1 Unit x 50%] = 10 hrs

  • Remaining Hrs = 24 – 10 = 14 hrs

  • Fleet Capacity = 14 Hrs x 2,000 tph x 50% = 14,000 tonnes

If you now assume you have 2 machines in the fleet and a delay of 2 hrs is inserted or included for a safety meeting then the fleet capacity will be computed as follows:

  • Available Hrs = 22 hrs

  • Operating Hrs = 10,000 tonnes /[2,000 tph x 2 Units x 50%] = 5 hrs

  • Remaining Hrs = 22 -5 = 17 hrs

  • Fleet Capacity = 17 hrs x 2,000 tph x 2 units x 50% = 34,000 tonnes

The actual start and end times for the Time Period, Non Work time and Planned Maintenance events are used to determine the Scheduled Hours. These events may overlap and this is taken into consideration when calculating the available operating hours.

The capacity of a Machine Class for a given time period is determined from the available operating hours and the rated capacity. The Rated capacity is entered in the Haul Truck Settings.

Formatting Options

Right-click the grid to see the following menu options:

Grid FormatDisplay the Grid Format screen. See Grid Format.
Show All PeriodsDisplay scheduled stockpile material for all periods.
Show FleetDisplays fleet information.
Copy to Clipboard

Copy the contents of the displayed grid to the clipboard. Data can be pasted in Excel, for example.

Related topics and activities