  • In the Scheduling Setupdialog, select any of the items in the Destinations menu group, including existing destinations.

  • In the Update Schedule dialog, select the browse button next to Destinations (restricted menus system, limited functionality will be available).

This topic relates to functionality found on the Destination General Settings panel. Information displayed in this section will relate to the currently selected destination.

Each destination type can have an associated operational cost per period. The cost is defined per tonne using the table provided.

Whilst these settings can be set for any destination type, they refer to a different type of cost; processing, rehandling (stockpiles) or rehabilitation (dumps). Data entry format is the same for all destination types.


Field Details:

Costs grid:

End Period: based on the currently defined calendar, select the period that represents the final one for which the specified cost applies. If no previous period cost is defined, the current Cost/Tonne will be applied for all periods from the start of mining up to and including the specified End Period.

Cost/Tonne: enter the value that will be associated with the defined period range.