Define stockpile supply settings |
Stockpile Supply Settings
To access this dialog:
-
In the Scheduling Setupdialog, select or add a stockpile destination type and enable the Supply tab.
The Supply panel
is used to define the initial and subsequent periods' material mass,
density and grade/quality settings. It is part of the settings defined
for a stockpile destination type. It
represents some of the settings defined for a stockpile destination
type.
Field Details:
The following fields are available::
Period: select a period number from the dropdown; default first period is 'Initial'.
Tonnes: enter a material mass value (tonnes) for the selected period.
Density: enter a material density value (g/t) for the selected period.
Numeric Field 1, 2, 3 etc...: enter values for the various material attribute fields (e.g. rock type codes (e.g. NLITH), grades (e.g. AU)) for the selected period.
If theMaximum Capacity group's Limited To parameter is set to a value which is smaller than the Tonnes value for a specific Period on this panel, pressing OK will display the warning "Maximum Capacity exceeded by Stockpile Supply". The Supply grid is populated with accumulated values that are not used with machines. For more information on how accumulated field values are defined and used, click here. |